Lindo Channel Recharge Feasibility
Our Plan
- Assess feasibility of enhancing natural recharge along the Lindo Channel in Chico.
Project Outcomes:
- Develop Recharge Feasibility Study
- Monitoring Network
- Stakeholder Engagement
Updates on Tasks during 4/1/24 - 8/31/24:
- Project is within budget.
- Schedule has been slightly delayed but overall is on track
Consultant Progress on Tasks Includes:
- Reviewed water rights to assist in developing the flow thresholds for diversion.
- Reviewed AEM data and well logs for assessment of groundwater recharge potential.
- August 5th, consultant came for a site visit.
Next Steps
- Revising the project schedule
- Stakeholder meeting